Keywords:
Cross sea bridge; construction survey; control survey; setting out survey
跨海大桥;施工测量;控制测量;放样测量
Abstract:
Construction survey runs through the whole construction process, and
construction survey work is closely related to the construction quality. In this paper,
the construction survey of the sea crossing double track railway bridge in the first
phase of babiyan port development project in Kuwait is summarized, and the survey
technology adopted in this project is discussed, which provides reference for similar
bridge construction survey.
施工测量贯穿于整个建筑施工过程中,同时施工测量工作对于工程施
工质量有着密切的联系。本文通过结合科威特巴比延海港开发项目一期工程的
跨海双线铁路桥施工测量实例,对跨海大桥的施工测量进行了概述,同时探讨
了本工程中所采取的测量技术,为类似的桥梁施工测量工作提供参考实例。